October 2022:
Picture
Week 8 of Construction:

Pouring the footer for the elevator.

Picture
Week 10 of Construction:

Pouring concrete basement walls.

Picture

Picture

Picture
Working on the elevator area.

Picture
Grading work being done between the existing buildings.

Picture

Picture
Concrete distribution piping soars in the sky.

Picture

Week 11 of Construction:


Basement walls secure.

Picture

Picture

Picture

Picture

Picture

Picture
Elevator shaft continues to progress.

Picture

Picture